AQW 450/22-27 Written question to the Minister of Education
To ask the Minister of Education for an update on the new build for Portadown Integrated Primary School.
Asked by Eóin Tennyson MLA on 24 May 2022
- Answered
- Written
- Tabled
- 24 May 2022
- Answer due by
- 10 June 2022
- Answered
- 10 June 202217 days after tabling
- Department
- Department of Education
- Priority question
- No
Answer
The appointment of an Integrated Consultant Team to carry out the design of the proposed Portadown Integrated Primary School was concluded in February 2022.
The Integrated Consultant Team is now working on the early stages of the design process which will then allow my Department to develop a business case to identify the preferred option for the project.