AQW 46063/22-27 Written question to the Minister of Education

To ask the Minister of Education for an update on any progress made on the new build on Mandeville Road for Portadown Integrated Nursery and Primary School.

Asked by Eóin Tennyson MLA on 12 May 2026

  • Answered
  • Written
Tabled
12 May 2026
Answer due by
28 May 2026
Answered
22 May 202610 days after tabling
Department
Department of Education
Priority question
No

Answer

The new build project is well advanced with the technical design (RIBA Stage 4) complete and planning approval for the project in place. Agreement in principle, has been reached with Armagh City, Banbridge and Craigavon Borough Council regarding the purchase of the Mandeville Road, Portadown site, which is progressing through the formal conveyance process.

However, following the site acquisition the project cannot progress to the construction stage until there is sufficient capital budget availability.

I continue to make the case for increased and sustained funding for Education, to permit this and many other much needed new school build projects to proceed to construction as soon as possible.