AQW 21005/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure for an update on the estimated timeline for the construction of Moylinn Footbridge, Craigavon.

Asked by Eóin Tennyson MLA on 21 January 2025

  • Answered
  • Written
  • After due date
Tabled
21 January 2025
Answer due by
5 February 2025
Answered
7 February 202517 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

My Department remains committed to taking forward the replacement of Moylinn East Footbridge. I can confirm that the contract tender process has now concluded, and it is expected that a full contract award, subject to any legal challenges, will be made by the end of January 2025.

At this time my Department does not have a scheme commencement date, although my officials will continue to liaise directly with the appointed contractor in order to find a suitable window for the commencement of works onsite.