AQW 6460/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure for an update on when work will commence on the redevelopment of Lurgan train station.

Asked by Eóin Tennyson MLA on 14 February 2024

  • Answered
  • Written
Tabled
14 February 2024
Answer due by
29 February 2024
Answered
26 February 202412 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

Following the approval by my Department of the Strategic Outline Case in June 2023, Translink is developing an Outline Business Case for this major project which is due to be submitted to my Department later this year.

Subject to the availability of funding and approval of appropriate business cases, and other statutory approvals, the new station should be scheduled to commence construction in the 2026/27 financial year.

Official sources