AQW 6058/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure for an updated timeline for the reinstatement of the Moylinn East Footbridge, Craigavon.

Asked by Eóin Tennyson MLA on 9 February 2024

  • Answered
  • Written
Tabled
9 February 2024
Answer due by
26 February 2024
Answered
21 February 202412 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

The Department remains committed to taking forward the replacement of Moylinn East Footbridge which will be subject to the completion of a business case, the need to secure funding, and statutory processes such as planning permission. It is hoped that planning will be in place within the next 6 months, to allow the project to be procured, subject to available funding.

Official sources